Application Migration

Last reviewed: August 2026

This is the work of moving applications and infrastructure from on-premises or another cloud into the cloud. It’s not simply copying VMs — it’s a process of re-evaluating the entire application’s architecture, dependencies, and operational model.

The 7R framework, proposed by Gartner and extended by AWS, is the standard for classifying migration strategies per workload.

Strategy Description Difficulty Effect
Retire Discontinue a workload that’s no longer needed Low Immediate cost savings
Retain Keep it on-premises (hybrid) Low No migration cost
Relocate Move as-is at the hypervisor level (e.g., VMware Cloud on AWS) Low Fast transition with minimal change
Rehost VM-level Lift & Shift Low Fast transition, limited cloud benefits
Replatform Partial transition to managed services (e.g., DB to RDS) Medium Reduced operational burden
Repurchase Switch to SaaS (e.g., a homegrown CRM → Salesforce) Medium Delegated operational responsibility
Refactor Redesign as cloud-native (serverless, microservices) High Maximizes scalability/efficiency
Situation Recommended strategy
Tight data center exit deadline Relocate or Rehost
Low business value, short-lived workload Retire
Functionality already available as a commercial solution Repurchase (SaaS)
Core workload where you want to maximize cloud benefits (scalability, cost) Refactor
Legacy system that needs stable operation with no changes Retain
Want to reduce operational burden while keeping the code Replatform

A comparison of the two most common options: Rehost (Lift & Shift) and Refactor.

Item Rehost (Lift & Shift) Refactor (cloud-native)
Migration duration Weeks to months Months to years
Development cost Low (minimal change) High (redesign/reimplementation)
Operational cost Similar to on-premises Can be reduced via cloud optimization
Scalability Limited (VM-based) High (serverless, horizontal scaling)
Disaster recovery Retains existing approach Cloud-native HA/DR
Risk Low High (redesign may fail)
Leveraging cloud benefits Limited Maximal
Data center exit deadline Can meet even short deadlines Requires a long timeframe

Large-scale migration is a project that goes through multiple phases.

Phase Key activities
1. Discovery Collect inventory — identify servers, applications, dependencies, and usage
2. Assessment Decide the 7R strategy per workload, estimate cost, analyze risk
3. Planning Decide migration order (waves), rollback plan, downtime budget
4. Landing Zone Build the cloud account/network/security foundation (see Landing Zone)
5. Migration Perform the actual data/application transfer
6. Validation Performance/functional testing, user acceptance testing
7. Cutover Traffic switchover, heightened monitoring
8. Optimize Optimize the cloud environment (cost, performance, security)

Migrating hundreds or thousands of workloads at once is risky. Migration is typically carried out in waves.

  • Pilot wave — Build experience with simple, low-risk workloads (e.g., internal tools, dev environments)
  • Core waves — Group applications and migrate them sequentially
  • Critical wave — Migrate business-critical workloads last (after sufficient validation)

Production workloads need to minimize downtime.

Technique Description When to use
Continuous block-level replication Continuously replicates changed blocks from the source VM to the target The default approach for most VM migration tools
Blue/Green cutover Run old and new infrastructure in parallel, then switch via DNS/LB Web services, APIs
Database CDC Continuously replicate DB changes so cutover completes within minutes DB migration
Phased cutover Gradual transition by user/region/feature Services with large user bases

Items to verify at the actual cutover moment.

  • Data integrity verification complete (checksums, record counts)
  • Application functional testing complete
  • Performance benchmarks meet or exceed the existing environment
  • Security settings verified (IAM, firewall, encryption)
  • Backup/DR configuration complete
  • Monitoring and alerting confirmed to be working
  • Rollback plan and rollback decision point determined
  • Stakeholders notified and Go/No-Go approval obtained
  • Cutover time window confirmed (weekend/night)
  • Response staff on standby in case of an incident
Vendor Product Capability
AWS Application Discovery Service Agent-based/agentless on-premises inventory collection
AWS Migration Hub Central migration dashboard
Azure Azure Migrate Assessment plus integrated server/DB migration
Google Cloud Migration Center Portfolio assessment, dependency mapping
OCI Cloud Migrations Integrated assessment and execution
Vendor Product Capability
AWS Application Migration Service (MGN) Block-level replication. Minimal-downtime Rehost
Azure Azure Migrate: Server Migration VMware/Hyper-V/physical servers → Azure VM
Google Cloud Migrate to Virtual Machines VMware/AWS/Azure → Compute Engine
OCI OCI Cloud Migrations VMware/AWS → OCI
Vendor Product Capability
AWS App2Container Containerize Java/.NET apps
Azure Migrate to containers ASP.NET/Java → AKS
Google Cloud Migrate to Containers VM → GKE containers
  • Starting migration without Discovery/Assessment — Without understanding dependencies and traffic patterns, failures occur post-cutover and rollback becomes necessary.
  • Migrating workloads before a landing zone exists — Moving without account structure, networking, IAM, and a tagging scheme in place means everything has to be rebuilt later.
  • Trying to Refactor all workloads at once — Schedules collapse and quality issues arise. For most, Rehost followed by gradual improvement is more realistic.